Tender pricing document
The tender pricing document sets out the way in which the design team and client wish to review the breakdown of the overall tender prices provided by tendering contractors. It is effectively an unpriced bill of quantities.
It generally follows the format of the cost plan that has been developed at this stage (the pre-tender estimate), however, the preliminaries, particularly staff costs, may be broken down in more detail.
The objective of the tender pricing document is to:
- Enable like-for-like comparison between tenders and the cost plan (pre-tender estimate).
- Enable the cost consultant to assess where value lies within the different tenders (such as foundations or finishes) allowing assessment of value for money.
- Identify any significant differences in pricing between tenderers to ensure the design has been correctly interpreted.
- Identify areas of savings that might be negotiated with tenderers while still in competition.
- Form the financial basis of the tender report.
The completed tender pricing document is effectively a priced bill of quantities. It sets out the tenderer's rates, costs and totals and constitutes the tenderer's complete offer.
NB: On design and build projects, there may not be a tender pricing document, and instead, a contract sum analysis might be prepared by the contractor.
See also: Tender price appraisal.
[edit] Related articles on Designing Buildings
- Accounting.
- Approximate quantities cost plan.
- Bills of quantities.
- Cash flow.
- Contract sum.
- Contract sum analysis.
- Cost consultant.
- Cost plan.
- Elemental cost plan.
- Initial cost appraisals.
- New Rules of Measurement.
- Pre-tender estimate.
- Spon's Price Book.
- Tender cost.
- Tender documentation.
- Tender price appraisal.
- Types of bill of quantities.
- Without quantities.
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.
Comments